DOCUMENTATION: Recovery Milestones
Day of Year |
Date |
Time UT |
Day from ESR 7 |
Events |
176 |
25-jun-98 |
04:38 |
- |
Emergency Sun Reacquisition (ESR7) |
176 |
25-jun-98N |
04:43 |
- |
Interruption of Mission |
204 |
23-jul-98 |
10:00 |
28 |
Confirmation of Orbit Position and Spacecraft Spin Rate by Arecibo and DSN Radar |
215 |
3-aug-98 |
22:51 |
39 |
Reception of Spacecraft Carrier Signal by DSN |
220 |
8-aug-98 |
23:14 |
44 |
Reception of Spacecraft Telemetry |
224 |
12-aug-98 |
23:39 |
48 |
Begin Thawing of Hydrazine Tank |
240 |
28-aug-98 |
23:02 |
64 |
End Thawing of Hydrazine Tank |
242 |
30-aug-98 |
66 |
Begin Thawing of Hydrazine Lines |
|
259 |
16-sep-98N |
05:45 |
83 |
Start of Attitude Recovery |
259 |
16-sep-98 |
18:29 |
83 |
ESR 8 |
259 |
16-sep-98 |
18:30 |
83 |
SOHO lock on Sun |
266 |
21-sep-98 |
16:58 |
90 |
SOHO in RMW |
268 |
25-sep-98 |
17:30 |
92 |
Orbit Correction (first segment) |
268 |
25-sep-98 |
19:52 |
92 |
SOHO in Normal Mode |
278 |
5 Oct 98T |
18:21 |
102 |
Start of Instrument Recommissioning |
309 |
5 Nov 98 |
|
133 |
Completion of Instrument Recommissioning |