More SOHO Recovery Updates


  • The SOHO Recovery page.
  • List of acronyms used in the SOHO project
    30 September 1998

    Spacecraft status remains nominal. Bi-monthly Attitude Control Unit (ACU) memory dumps were performed, an ACU monitoring patch was uplinked, and a test of Gyro C was performed. The Gyro C test indicated that the gyro motor was spinning; however no output from the gyro was received.

    Central Data Management Unit (CDMU) memory dumps continue today. A star sensor unit (SSU) patch, will be performed tomorrow morning.

    Updates of ESR recovery procedures have been defined such that recovery is based on one gyro only. ESR warning flag will be enabled today.


    29 September 1998

    Activities yesterday included a change in the guide star. The one being used now is magnitude 5.7, in slot 1. Also, there were group dumps and configuration monitoring. We had some problems while commanding through DSS27, as only 200 Watts uplink power was available. Uploading of COBS and SSU patches was postponed until today, to use DSS24 instead.

    In the morning meeting today there was an overview of the current plans for instrument re-commissioning, with an schedule some 30 working days long.

    Next orbital maneuver is scheduled for October 14.


    25 September 1998, evening update

    SOHO is back in normal mode.

    The first activity of the day was a roll trim that was carried out at 13:30 UT. Afterwards, receiver 1 was tested and locked while using the high gain antenna. Receiver 1 is used for ranging in normal mode.

    A station keeping maneuver was completed in two burns along the X axis, direction away from the Sun. The first burn was 2 minutes and the second one 47.5 minutes long. FDF estimates that the resulting delta-vee was within 1% of the desired value of -6.2 m/s.

    After the maneuver was completed, SOHO was commanded to high rate telemetry and then on to normal mode. The spacecraft entered normal mode at 19:52:58 UT.

    A period of two weeks of ranging starts now. Next maneuver, therefore, will be scheduled for some time after October 8.

    Next week will continue the recomissioning activities of spacecraft elements not used during the recovery maneuver. Also, there will be patch uploads and further tests of gyros A and C.


    25 September 1998

    The thermal status of both the service and payload modules of the spacecraft is now nominal.

    Receiver 1 was locked twice using the low gain antenna, 18 KW uplink power with a 26m DSN antenna, and wide frequency sweeps.

    A star map was collected and dumped using the star sensor unit 1 (SSU1). FDF reports that SSU1 behaviour is nominal. The absolute roll attitude was determined to be 50.84 degrees.

    SOHO is now in medium rate telemetry, using the high gain antenna (HGA), receiver 2 and transmitter 1. The signal level at DSS24 was -116 dBm, which indicates good HGA pointing.

    Overnight, the tape recorder was set on record during 3 hours, and the data collected were dumped afterwards. The analysis of the dump shows good statistics. The same was done with the solid state recorder, but the analysis of the dump is still under way.

    The procedures for a station keeping maneuver have been prepared and verified.


    24 September 1998

    The DHSS problem found the day before yesterday was not a hardware issue, but due to the uplink of Mode 3 commands a little bit too fast. Once the timing of this commands was sligthly changed, the script to transition the spacecraft from ESR mode to RMW (through ISA and FSA modes) was run again yesterday morning without a glitch. The spacecraft is in RMW mode, using a 4.7 magnitude star, since 16:58 UT, yesterday. While on FSA, both SSUs were successfully checked out.

    Other activities accomplished were the uplinking of ACU patches 5 and 6, and the warm start up recovery using the nominal recovery procedure, so DHSS is now back in the nominal branch.


    23 September 1998

    Yesterday, there was an attempt to transition the spacecraft from ESR to ISA, then to FSA and on to RMW mode. However, it was not successful for the following two reasons.

    While on ISA mode and preparing the transition to FSA, a Mode 3 command with data words to change the limit for RRAD was sent to the spacecraft. Unfortunately, while building the command, the CMS on the ground shifted the value of this limit 8 bits to the right, dividing it by 256, and making it very close to zero. As soon as this command was uplinked, a roll rate anomaly was triggered on board and the spacecraft transitioned itself to ESR mode again.

    Later in the afternoon, when running the script again, a DHSS error, under investigation, prevented the completion of the activities when it caused a COBS warm start up. This event had no effect on the spacecraft thermal configuration.

    Today, a spacecraft emergency was declared in order to secure DSN coverage until SOHO is, once again, in nominal mode.

    Thrusters 7 and 8 (B side) were successfully tested when SOHO was on ISA mode. This completed the tests of the propulsion subsystem.


    22 September 1998

    Yesterday, both Fine Pointing Sun Sensors (FPSS) were checked out and found to be in good health. Also, there were two 0.1 deg/s corrections of the roll rate of the spacecraft.

    The procedures to transition from ESR to ISA and from ISA to RMW are being worked out.


    21 September 1998

    On Saturday evening Gyro B was tested and was found to be fine. Gyro C was showing intermittent anomalies in its behaviour. An investigation on this matter is under way. It is worth noting that both gyros with problems, A and C, were warm at the time of the loss of attitude in June while Gyro B was cold.

    The roll rate anomaly detection (RRAD) has been tested also on Saturday and it is working fine. The reaction wheels are being kept at 1500 rpm and the roll rate of the spacecraft never surpassed 0.1 deg/s.

    Plans for testing of thursters 7 and 8 on the B side, and then reconfiguring the spacecraft to the A side are under preparation.


    19 September 1998

    Another good day: Automatic Gain Control (AGC) estimate of the spacecraft roll rate is about -0.1 deg/sec.


    18 September 1998

    This was a good day:


    17 September 1998

    Spacecraft stability continues to be excellent. The roll rate has been less than 0.2 deg/sec and has now been stabilized to almost zero by thruster firings. An attempt to restart gyro A has been unsuccessful and a reconfiguration to gyro C is planned for tomorrow.


    16 September 1998

    The first but important step in the SOHO recovery has been successfully completed today. Sun pointing (without roll control) has been achieved at 18:30 UT. All operations went according to plan. The experiment substitution heaters were switched on 42 minutes after the ESR was triggered.

    During the run up of gyro A an anomaly was detected which is currently under investigation. Meantime the S/C is maintaining the ESR in stable condition with no sign of roll rate being out of limits. The S/C is expected to be stable over night.

    Details of the attitude recovery maneuver run today can be found here.


    15 September 1998

    The heating phases of the batteries charging/heating cycles have been reduced by 2 hours. The cycles are now 2 hr charging and 5 hr heating. With these settings the batteries are expected to be fully charged for the attitude recovery maneuver by 01:00 UT tomorrow. Due to this change, both battery temperature and voltage have raised slightly while propulsion subsystem temperatures have decreased a little bit.

    The payload RTU has been switched on briefly today at 16:00 UT to take a reading of the payload module thermistors. The payload temperatures can be found in the table included below.

    After reviewing the simulation run today, it was decided to run the attitude recovery maneuver tomorrow. The solution chosen to recover the attitude of the spacecraft consists of (times are subject to change):

      Time UT Description
      
     1. 06:00 Additional warming up of the propulsion subsystem.
     2. 08:00 Intermediate check of telemetry.
     3. 10:30 Adjustment of Sun heating mode before maneuvers.
     4. 12:00 Thrusters tests.
     5. 12:30 Thruster 4B despin calibration.
     6. 13:05 Thruster 4B despin 1 (down to 2.4 deg/s).
     7. 13:50 Data collection and procedure uploading.
     8. 14:10 Data evaluation.
     9.       FOT load update prior to despin 2.
    10. 15:15 Thruster 4B despin 2 (down to 0.9 deg/s).
    11. 16:35 Switch on FDE and enable/reset min/max monitoring.
    12. 17:09 Data evaluation.
    13.       Battery management.
    14. 17:14 Preparation of ESR.
    15.       Check spacecraft status before ESR.
    16. 18:09 Go for ESR given subsystem by subsystem.
    17. 18:10 Thermal control management.
    18.       Upload timetags to enable standard monitoring functions.
        T1    ESR trigger.
    19. T1+3  ESR without on board roll control.
    20.       Set up payload configuration (RTU, PPDU on).
    21.       Trigger COBS reboot and reset thermal control.
    22.       Thermal adjustment after ESR (including EXP subs heaters).
    23.       Spin up and selection of gyro for ground roll control.
    

    Every step has criteria for success and contingency plans defined.

    After the end of these activities, the spacecraft will have on board Sun pointing control. The roll rate will be controlled from ground.


    
    PLM Temperatures on 9 August, 28 August, 9 September and 15 September 1998
    
    MNEMONIC   Limit	Temperature [deg C]
    				
    			8/9/98	 8/28/98     9/9/98    15/9/98
                 CDS
    		
    QTCI1A	   10/30	78.57      48.23      15.14      -4.17
    QTCI1B	   10/30	78.57      47.60      14.85      -4.47
    QTCR1	    5/35	 1.91      -6.54     -13.98     -18.83
    QTCR2	    6/30	35.28      13.13      -3.88     -12.70
    QTCR3	    6/34	41.92      12.56      -9.50     -19.20
    
    
              CELIAS
    
    QTFI1A	  -15/35	42.78      22.95       6.93      -4.56
    QTFI1B	  -15/35	41.91      22.95       7.32      -3.57
    QTFI2A	  -40/40	35.37      22.95      13.96       1.46
    QTFI2B	  -40/40	34.93      22.95      13.96       1.07
    QTFI3A	  -15/35	41.91      24.12       6.93      -3.07
    QTFI3B	  -15/35	41.91      23.73       6.54      -3.57
    QTFR1	    5/35	 3.35      -4.47     -11.74     -16.63
    QTFR2	    5/35	 3.92      -5.07     -12.38     -18.10
    QTFR3	    5/35	 9.96      -0.68      -9.50     -15.90
    QTFR4	    7/30	16.74       1.91      -9.50     -17.00
    QTFR5	    8/36	-5.65     -13.02     -18.83     -21.40*
    Q11	    5/35	10.54      -1.54     -11.10     -17.37
    	
    
               CEPAC
    
    QTHI1A     10/25       -21.40*    -21.40*    -21.40*    -21.40*
    QTHI1B     10/25       -21.40*    -21.40*    -21.40*    -21.40*
    QTHI2     -13/21       -21.67     -22.22     -24.44     -26.11
    QTHI3       0/30       -19.57     -15.58     -16.27     -17.73
    QTHR1       5/35       -11.10     -15.58     -20.30     -21.40*
    QTHR2       8/31        -4.47     -11.74     -18.10     -21.40*
    QTHR3      -3/34       -21.40*    -21.40*    -21.40*    -21.40*
    QTHR4       4/33       -11.10     -17.00     -21.40*    -21.40*
    QTHR5       5/35        -7.43     -13.98     -19.57     -21.40*
    
    
                GOLF
    
    QTGI1A      5/40       -21.40*    -16.27     -18.47     -21.40*
    QTGI1B      5/40       -21.40*    -16.27     -18.10     -21.40*
    QTGR1       5/35         3.64      -5.06     -12.38     -17.73
    QTGR2      10/25        39.39      14.56      -2.40     -11.42
    QTGR3       5/35        40.03      12.83      -5.65     -14.94
    
    
           LASCO/EIT
    
    QTLI1A      5/30        33.19      22.95      14.35       8.49
    QTLI1B      5/30        33.62      23.72      15.13       9.28
    QTLI2A     10/30       -49.20*    -49.20*    -46.17     -46.17
    QTLI2B     10/30       -49.20*    -47.68     -44.66     -44.66
    QTLI3A    -10/20       -49.20*    -49.20*    -47.69     -46.17
    QTLI3B    -10/20       -49.20*    -49.20*    -49.20*    -47.69
    QTLR1       5/35        -3.58     -11.42     -16.63     -20.67
    QTLR2       5/35       -15.26     -20.67     -21.40*    -21.40
    QTLR3       5/35         4.21      -3.58     -10.46     -15.58
    
    
                 MDI
    
    QTMI1A     10/35       -21.40*	  -18.47     -20.67     -21.03
    QTMI1B     10/35       -21.40*    -15.58     -17.73     -18.10
    QTMI1C     10/41       -21.40*    -16.63     -18.83     -19.20
    QTMI1D   -105/40       -53.33     -43.33     -48.33     -46.67
    QTMI2       0/40       -22.15     -23.60     -24.32     -25.05
    QTMR1       5/35        -2.40      -9.20     -14.94     -19.57
    QTMR2       5/35        -3.58      -8.91     -12.70     -15.90
    
    
               SUMER
    
    QTSI1A     15/27       -21.40*    -21.40*    -21.40*    -21.40*
    QTSI1B     15/27       -21.40*    -21.40*    -21.40*    -21.40*
    QTSI2A      5/25       -21.40*    -19.93     -21.40*    -21.40*
    QTSI2B      5/25       -21.40*    -19.56     -21.03     -21.40*
    QTSR1       5/35        -0.96      -8.91     -14.94     -19.20
    QTSR2       5/34       -16.27     -21.40*    -21.40*    -21.40*
    QTSR3       2/27       -13.98     -19.57     -21.40*    -21.40*
    
    
                SWAN
    
    QTNI1A      5/30        44.45      37.50      30.09      23.04
    QTNI1B      5/30        45.71      39.39      31.93      24.90
    QTNI2A      5/30       -21.40*    -21.40*    -21.40*    -21.40*
    QTNI2B      5/30       -21.40*    -21.40*    -21.40*    -21.40*
    QTNR1       5/35        29.34      20.45      11.11       3.92
    QTNR2       5/35       -21.40*    -21.40*    -21.40*    -21.40*
    QTNR3       6/31       -13.66     -19.57     -21.40*    -21.40*
    
    
                UVCS
    
    QTUI1A      0/40        -5.65      -6.54      -8.61     -12.06
    QTUI1B      0/40        -5.36      -6.25      -8.02     -11.42
    QTUR1       5/35        -5.06      -9.82     -15.58     -20.30
    QTUR2       5/30        37.13      11.11      -8.32     -17.73
    
    
               VIRGO
    
    QTVR1       3/30        -9.50     -15.58     -21.03     -21.40*
    QTVR2       5/33       -18.83     -21.40*    -21.40*    -21.40*
    
    
    -----------
    Note: * means: end of sensor measurement range
    
    
    

    14 September 1998

    There were no changes in the spacecraft. Propulsion system temperatures remain stable. The heating phases of the charge/heating cycles have been shortened to 7 hours.

    The verification of the procedures for attitude recovery was completed today. A rehearsal of the attitude recovery maneuver is scheduled for tomorrow morning.


    12 September 1998

    There were no changes in the spacecraft. Battery charge and temperature, and propulsion system temperatures are stable and being maintained using the 2 hour charging and 8 hour heating cycles started on September 10. This mode will change to two cycles of 2h/5h right before the attitude recovery maneuver to increase the charge of the batteries.

    Receiver 1 was tested twice without accomplishing lock.

    The definition, coding, and verification of attitude recovery and contingency procedures continues.


    11 September 1998

    Battery charge and propulsion system temperatures are being maintained. Communication with the spacecraft is carried out using transponder 2 and the +Z low gain antenna. The preparation of the procedures for the attitude recovery maneuver is progressing.


    10 September 1998

    Preparations for the attitude recovery are continuing. The charge state of the batteries is good. We have therefore changed from a 2 hour charging / 5 hour heating cycle to a 2 hour charging / 8 hour heating cycle. Transponder 2 was successfully switched from the -Z low gain antenna to the +Z low gain antenna.

    Thermal models showing the temperature behaviour of the instruments after reacquisition of nominal sun pointing attitude can be found at http://sohowww.nascom.nasa.gov/operations/Recovery/PLM_temps/ and http://sohowww.estec.esa.nl/operations/Recovery/PLM_temps/.


    9 September 1998

    Data was collected from several subsytems in preparation for the attitude recovery maneuver, which is planned for next week. New PLM temperature readings are attached. A test with transponder 1 indicates that the +Z low gain antenna is now also in the field of view of the Earth. Battery charge and propulsion subsystem temperatures are being maintained.

    ----------------------------------------------------------------------
    PLM Temperatures on 9 August, 28 August and 9 September 1998
    
    MNEMONIC	Limit		Temperature [deg C]
    				
    				8/9/98		8/28/98		9/9/98
    		CDS
    		
    QTCI1A		10/30		78.57		48.23		15.14
    QTCI1B		10/30		78.57		47.60		14.85
    QTCR1		5/35		1.91		-6.54		-13.98
    QTCR2		6/30		35.28		13.13		-3.88
    QTCR3		6/34		41.92		12.56		-9.50
    
    
    		CELIAS
    
    QTFI1A		-15/35		42.78		22.95		6.93
    QTFI1B		-15/35		41.91		22.95		7.32
    QTFI2A		-40/40		35.37		22.95		13.96
    QTFI2B		-40/40		34.93		22.95		13.96
    QTFI3A		-15/35		41.91		24.12		6.93
    QTFI3B		-15/35		41.91		23.73		6.54
    QTFR1		5/35		3.35		-4.47		-11.74
    QTFR2		5/35		3.92		-5.07		-12.38
    QTFR3		5/35		9.96		-0.68		-9.50
    QTFR4		7/30		16.74		1.91		-9.50
    QTFR5		8/36		-5.65		-13.02		-18.83
    Q11		5/35		10.54		-1.54		-11.10
    	
    
    		CEPAC
    
    QTHI1A		10/25		-21.40*		-21.40*		-21.40*
    QTHI1B		10/25		-21.40*		-21.40*		-21.40*
    QTHI2		-13/21		-21.67		-22.22		-24.44
    QTHI3		0/30		-19.57		-15.58		-16.27
    QTHR1		5/35		-11.10		-15.58		-20.30
    QTHR2		8/31		-4.47		-11.74		-18.10
    QTHR3		-3/34		-21.40*		-21.40*		-21.40*
    QTHR4		4/33		-11.10		-17.00		-21.40*
    QTHR5		5/35		-7.43		-13.98		-19.57
    
    
    		GOLF
    
    QTGI1A		5/40		-21.40*		-16.27		-18.47
    QTGI1B		5/40		-21.40*		-16.27		-18.10
    QTGR1		5/35		3.64		-5.06		-12.38
    QTGR2		10/25		39.39		14.56		-2.40
    QTGR3		5/35		40.03		12.83		-5.65
    
    
    		LASCO/EIT
    
    QTLI1A		5/30		33.19		22.95		14.35
    QTLI1B		5/30		33.62		23.72		15.13
    QTLI2A		10/30		-49.20*		-49.20*		-46.17
    QTLI2B		10/30		-49.20*		-47.68		-44.66
    QTLI3A		-10/20		-49.20*		-49.20*		-47.69
    QTLI3B		-10/20		-49.20*		-49.20*		-49.20*
    QTLR1		5/35		-3.58		-11.42		-16.63
    QTLR2		5/35		-15.26		-20.67		-21.40*
    QTLR3		5/35		4.21		-3.58		-10.46
    
    
    		MDI
    
    QTMI1A		10/35		-21.40*		-18.47		-20.67
    QTMI1B		10/35		-21.40*		-15.58		-17.73
    QTMI1C		10/41		-21.40*		-16.63		-18.83
    QTMI1D		-105/40		-53.33		-43.33		-48.33
    QTMI2		0/40		-22.15		-23.60		-24.32
    QTMR1		5/35		-2.40		-9.20		-14.94
    QTMR2		5/35		-3.58		-8.91		-12.70
    
    
    		SUMER
    
    QTSI1A		15/27		-21.40*		-21.40*		-21.40*
    QTSI1B		15/27		-21.40*		-21.40*		-21.40*
    QTSI2A		5/25		-21.40*		-19.93		-21.40*
    QTSI2B		5/25		-21.40*		-19.56		-21.03
    QTSR1		5/35		-0.96		-8.91		-14.94
    QTSR2		5/34		-16.27		-21.40*		-21.40*
    QTSR3		2/27		-13.98		-19.57		-21.40*
    
    
    		SWAN
    
    QTNI1A		5/30		44.45		37.50		30.09
    QTNI1B		5/30		45.71		39.39		31.93
    QTNI2A		5/30		-21.40*		-21.40*		-21.40*
    QTNI2B		5/30		-21.40*		-21.40*		-21.40*
    QTNR1		5/35		29.34		20.45		11.11
    QTNR2		5/35		-21.40*		-21.40*		-21.40*
    QTNR3		6/31		-13.66		-19.57		-21.40*
    
    
    		UVCS
    
    QTUI1A		0/40		-5.65		-6.54		-8.61
    QTUI1B		0/40		-5.36		-6.25		-8.02
    QTUR1		5/35		-5.06		-9.82		-15.58
    QTUR2		5/30		37.13		11.11		-8.32
    
    
    		VIRGO
    
    QTVR1		3/30		-9.50		-15.58		-21.03
    QTVR2		5/33		-18.83		-21.40*		-21.40*
    
    
    -----------
    Note: * means: end of sensor measurement range
    


    8 September 1998

    The batteries are fully charged. The propulsion subsystem temperatures are slowly improving.

    Three more experts from Europe have arrived at GSFC for the preparation of the attitude recovery. A review of the recovery scenario for final approval is planned for Thursday, 10 September 1998.


    7 September 1998

    Battery recharging continues. Propulsion subsystem temperatures are being maintained.

    Two alternative solutions which use fewer thrusters for attitude recovery are being studied:

    Solution A consists of:

    Solution B consists of:


    4 September 1998

    We are continuing to slowly recharge the batteries whilst trying to maintain the propulsion subsystem temperatures, which is proving to be a delicate balance.

    Alternative scenarios for the attitude recovery with reduced requirements on the propulsion and power subsystems are currently being studied.


    3 September 1998

    We are entering a cyclic battery charging phase while trying to maintain propulsion subsystem temperatures.


    2 September 1998

    Pipe heating continues. All the pipe heaters are currently switched on in sun-heating mode. Three of the Dual Thruster Modules (DTMs) appear to be thawed. Pressures in the tank and two propulsion branches are as predicted and steady.

    A test was performed on receiver #1 on the +Z low gain antenna. Lock was not achieved.

    A four step approach has been adopted for the attitude recovery:

    1. Gyro test
    2. Thruster test
    3. Despin of the S/C to low rate
    4. Triggering of ESR
    Details are being discussed by AOCS experts at GSFC, MMS-F Toulouse and MMS-UK Bristol. The schedule for these activities depends on the completion of thawing of the propulsion system and the time needed to fully recharge the batteries.


    1 September 1998

    Pipe heating is continuing. Three of four pipe sections of the propulsion subsystem are presently being heated while the tank temperature is being maintained at 10.5 deg C. Data from the propulsion instrumentation indicates nominal tank pressure. Propulsion branch pressures are as expected. Latch valve B has been closed to isolate pipes from the tank.

    A test with transmitter 1 on the +Z low gain antenna has been successful. Carrier signal was received for approximately 1 min 45 sec with expected fluctuations due to spacecraft spin.


    31 August 1998

    Heating of the first of four pipe sections continues. Pipe temperature and pressure are monitored in one hour intervals. The heating rate is being adjusted accordingly. Tank temperature is being maintained during pipe heating.


    30 August 1998

    Heating of the first of four pipe sections has commenced at 12:30 UT this morning after recharging the batteries for 37 hours. Tank temperature is 9.7 deg C. Shift working has been resumed to enable 24 hour monitoring of the pipe temperatures.


    28 August 1998

    Continued tank heating. Tank temperature reached 9 deg C at 19:02 UT. Will stop tank heating at 23 UT to recharge batteries for 36 hours. Will start pipe heating Sunday morning.

    The PRTU was briefly switched on at 15:05 UT to obtain another reading of the instrument temperatures (see attachment).

    ----------------------------------------------------------------------
    PLM Temperatures on 9 August 1998 and 28 August 1998
    
    MNEMONIC	Limit		Temperature [deg C]
    				
    				8/9/98		8/28/98
    		CDS
    		
    QTCI1A		10/30		78.57		48.23
    QTCI1B		10/30		78.57		47.60
    QTCR1		5/35		1.91		-6.54
    QTCR2		6/30		35.28		13.13
    QTCR3		6/34		41.92		12.56
    
    
    		CELIAS
    
    QTFI1A		-15/35		42.78		22.95
    QTFI1B		-15/35		41.91		22.95
    QTFI2A		-40/40		35.37		22.95
    QTFI2B		-40/40		34.93		22.95
    QTFI3A		-15/35		41.91		24.12
    QTFI3B		-15/35		41.91		23.73
    QTFR1		5/35		3.35		-4.47
    QTFR2		5/35		3.92		-5.07
    QTFR3		5/35		9.96		-0.68
    QTFR4		7/30		16.74		1.91
    QTFR5		8/36		-5.65		-13.02
    Q11		5/35		10.54		-1.54
    	
    
    		CEPAC
    
    QTHI1A		10/25		-21.40*		-21.40*
    QTHI1B		10/25		-21.40*		-21.40*
    QTHI2		-13/21		-21.67		-22.22
    QTHI3		0/30		-19.57		-15.58
    QTHR1		5/35		-11.10		-15.58
    QTHR2		8/31		-4.47		-11.74
    QTHR3		-3/34		-21.40*		-21.40*
    QTHR4		4/33		-11.10		-17.00
    QTHR5		5/35		-7.43		-13.98
    
    
    		GOLF
    
    QTGI1A		5/40		-21.40*		-16.27
    QTGI1B		5/40		-21.40*		-16.27
    QTGR1		5/35		3.64		-5.06
    QTGR2		10/25		39.39		14.56
    QTGR3		5/35		40.03		12.83
    
    
    		LASCO/EIT
    
    QTLI1A		5/30		33.19		22.95
    QTLI1B		5/30		33.62		23.72
    QTLI2A		10/30		-49.20*		-49.20*
    QTLI2B		10/30		-49.20*		-47.68
    QTLI3A		-10/20		-49.20*		-49.20*
    QTLI3B		-10/20		-49.20*		-49.20*
    QTLR1		5/35		-3.58		-11.42
    QTLR2		5/35		-15.26		-20.67
    QTLR3		5/35		4.21		-3.58
    
    
    		MDI
    
    QTMI1A		10/35		-21.40*		-18.47
    QTMI1B		10/35		-21.40*		-15.58
    QTMI1C		10/41		-21.40*		-16.63
    QTMI1D		-105/40		-53.33		-43.33
    QTMI2		0/40		-22.15		-23.60
    QTMR1		5/35		-2.40		-9.20
    QTMR2		5/35		-3.58		-8.91
    
    
    		SUMER
    
    QTSI1A		15/27		-21.40*		-21.40*
    QTSI1B		15/27		-21.40*		-21.40*
    QTSI2A		5/25		-21.40*		-19.93
    QTSI2B		5/25		-21.40*		-19.56
    QTSR1		5/35		-0.96		-8.91
    QTSR2		5/34		-16.27		-21.40*
    QTSR3		2/27		-13.98		-19.57
    
    
    		SWAN
    
    QTNI1A		5/30		44.45		37.50
    QTNI1B		5/30		45.71		39.39
    QTNI2A		5/30		-21.40*		-21.40*
    QTNI2B		5/30		-21.40*		-21.40*
    QTNR1		5/35		29.34		20.45
    QTNR2		5/35		-21.40*		-21.40*
    QTNR3		6/31		-13.66		-19.57
    
    
    		UVCS
    
    QTUI1A		0/40		-5.65		-6.54
    QTUI1B		0/40		-5.36		-6.25
    QTUR1		5/35		-5.06		-9.82
    QTUR2		5/30		37.13		11.11
    
    
    		VIRGO
    
    QTVR1		3/30		-9.50		-15.58
    QTVR2		5/33		-18.83		-21.40*
    
    
    -----------
    Note: * means: end of sensor measurement range
    


    27 August 1998

    Resumed tank heating at 15:03 UT after charging the batteries for 29 hours. Tank temperature at 19:05 UT: 7 deg C. Will continue tank heating until it reaches 10 deg C (expected for Saturday morning). Presently we plan to start pipe heating Sunday morning after topping up the batteries.


    26 August 1998

    The tank temperature continued to increase over night:
    02:00 UT: 3.0 deg C
    06:00 UI: 3.9 deg C
    10:00 UT: 5.3 deg C
    Switched of tank heating at 10:10 UT to recharge the batteries for 24 hours.


    25 August 1998

    Today appears to be the first sign of the completion of the hydrazine thawing of the tank: The tank temperature increased from 1.3 deg C to 1.9 and 2.3 deg C at 10:00 and 18:00 UT, respectively. Tank heating will continue until tomorrow morning at 10:00 UT when we will start recharging the batteries.

    ESA and MMS AOCS experts arrived today at GSFC for the preparation of the attitude recovery.

    Colleagues from the simulation section of ESA/ESTEC (TOS-EMM) have prepared two animations showing SOHO's estimated attitude on 23 August (45 deg) and 7 September (60 deg): http://sohowww.nascom.nasa.gov/operations/ESR7/attitude.html


    24 August 1998

    Tank heating continues.


    23 August 1998

    Stopped recharging the batteries and resumed tank heating at 02:00 UT.


    21 August 1998

    Stopped tank heating at 20:15 UT to recharge batteries for 30 hours. Will resume tank heating tomorrow night. Once the propellant in the tank has been brought to 10 deg C, we will start heating the pipes. After pipe heating, which will take about 2 days, there will be a gyro test, HPA test (in high power mode) and thruster test. The schedule for these activities is still under discussion.

    Prelmininary analysis of the ranging data indicates that we are very close to the predicted orbit before the momentum management on 24 June, i.e. the delta V disturbances experienced during ESR 5, 6 and 7 were very small. To give you an indication of how good the orbit still is: For an orbit correction on 15 September we would need only a few kg of hydrazine.


    20 August 1998

    Tank heating continues.


    19 August 1998

    Thawing of the tank is progressing. A new procedure to heat only in sunlight without discharging the batteries has been successfully tested. This procedure will be applied later to maintain thermal control of the propulsion subsystem while charging the batteries.


    18 August 1998

    Stopped recharging the batteries at 20:09 UT and resumed heating of the tank at 20:15 UT. Took 20 min of SAS-A data starting at 20:25 UT. Battery charge state and temperatures will be checked in 6 hour intervals.


    17 August 1998

    Thawing of the tank proceeded as planned. Heating was stopped at 19:05 UT to recharge the batteries.


    16 August 1998

    Thawing of the tank is proceeding as planned. A short switch-on test of the FDE (Failure Detection Electronics) has been successful.


    15 August 1998

    Thawing of the tank is proceeding as planned.


    14 August 1998

    Charging of the batteries continued until 20:05 UT. They reached the expected value of 46 V (approx. 65% of max capacity). At 20:17 UT the heaters of the tank were switched on again to continue thawing of the hydrazine. Temperatures and battery voltage are monitored in 4 hour intervals.


    13 August 1998

    The SAS data received on 11 August have been analyzed. It was confirmed that SOHO is spinning around an axis close to the Z axis at a rate of -6.9 deg/sec (rotation period 52.6 sec). The rotation vector is 1.8 deg from the Z axis towards the X axis and 7.6 deg from the Z axis towards the -Y axis. The angle between the rotation axis and the Sun is 36.7 deg.

    The X-band ranging on 11 August was not successful. The cause for the failure is still under investigation.

    Today we started ranging with SOHO. We had a total of four session where we acquired ranging data, each lasting a couple of minutes.

    Thawing of the tank has started yesterday evening at 22:39 UT. It was interrupted today at 20:03 UT in order to recharge the batteries. Analysis of the power data revealed a slightly negative power balance, i.e. we draw power from the batteries when the heaters are on. We therefore have to recharge the batteries from time to time. Batteries charged for 20 hours should have enough capacity to allow us to turn the heaters on for about 3 days. Presently we estimate that about two cycles of charging/heating will be necessary to thaw the hydrazine in the tank.


    12 August 1998

    Power, thermal, and propulsion experts from ESA/ESTEC, MMS-F and MMS-UK have arrived this morning.

    A detailed power budget has been established and a decision has been made to start thawing of the propellant in the tank this evening. The batteries' charge state and tank temperature will be carefully monitored to confirm power budget and thermal estimates. This monitoring required us to declare a spacecraft emergency in order to have continuous DSN contact.

    The SAS data acquired yesterday are still being analyzed at ESTEC, MMS-F and GSFC. Also no definitive results yet from yesterday's X-band ranging measurement.


    11 August 1998

    The S-band radar measurements planned for today could not be performed due to techical problems with the Arecibo transmitter. In the afternoon, DSS14 performed X-band ranging measurements for about an hour. At the time of writing of this report it was not clear whether we succeeded to obtain valid data.

    At 21 UT we successfully switched on Attitude Control Unit A (ACU-A) and Control Actuation Electronics A (CAE-A) which allowed us to get attitude data from the Sun Acquisition Sensors (SAS). 5 min of SAS data were acquired. Experts will analyze the data tonight to determine the exact attitude of the spacecraft. The telemetry session is still going on at this time (now for almost 1 1/2 hours). The FOT is monitoring the power status of the batteries, which seem to hold the power well.

    If the power balance proofs to be adequate, we will start to thaw out the propulsion subsytem tomorrow.


    10 August 1998

    On Sunday afternoon we had two more successful telemetry sessions, both with PRTU ON. To preserve resources, the first session was terminated through ground commands after 4 min 15 sec, in the second session telemetry was switched off after 5 min 1 sec. Experts at GSFC, ESA/ESTEC and MMS are analyzing the data. As expected, the spacecraft in general is cold. Of course, some units are warmer than normal. The tank is around 1 deg C, so the hydrazine probably is partially frozen.

    Attached you can find temperatures for the PLM units. Those annotated with a star have no meaning (out of sensor measurement range).

    Presently we are charging both batteries. As a safety precaution, charging of the batteries has been limited to 45 V.

    Propulsion, power, and AOCS experts are expected to arrive at GSFC later this week.

    PLM Temperatures on 9 August 1998
    
    MNEMONIC	Limit		Temperature [deg C]
    
    		CDS
    		
    QTCI1A		10/30		78.57
    QTCI1B		10/30		78.57
    QTCR1		5/35		1.91
    QTCR2		6/30		35.28
    QTCR3		6/34		41.92
    
    
    		CELIAS
    
    QTFI1A		-15/35		42.78
    QTFI1B		-15/35		41.91
    QTFI2A		-40/40		35.37
    QTFI2B		-40/40		34.93
    QTFI3A		-15/35		41.91
    QTFI3B		-15/35		41.91
    QTFR1		5/35		3.35
    QTFR2		5/35		3.92
    QTFR3		5/35		9.96
    QTFR4		7/30		16.74
    QTFR5		8/36		-5.65
    Q11		5/35		10.54
    	
    
    		CEPAC
    
    QTHI1A		10/25		-21.40*
    QTHI1B		10/25		-21.40*
    QTHI2		-13/21		-21.67
    QTHI3		0/30		-19.57
    QTHR1		5/35		-11.10
    QTHR2		8/31		-4.47
    QTHR3		-3/34		-21.40*
    QTHR4		4/33		-11.10
    QTHR5		5/35		-7.43
    
    
    		GOLF
    
    QTGI1A		5/40		-21.40*
    QTGI1B		5/40		-21.40*
    QTGR1		5/35		3.64
    QTGR2		10/25		39.39
    QTGR3		5/35		40.03
    
    
    		LASCO/EIT
    
    QTLI1A		5/30		33.19
    QTLI1B		5/30		33.62
    QTLI2A		10/30		-49.20*
    QTLI2B		10/30		-49.20*
    QTLI3A		-10/20		-49.20*
    QTLI3B		-10/20		-49.20*
    QTLR1		5/35		-3.58
    QTLR2		5/35		-15.26
    QTLR3		5/35		4.21
    
    
    		MDI
    
    QTMI1A		10/35		-21.40*
    QTMI1B		10/35		-21.40*
    QTMI1C		10/41		-21.40*
    QTMI1D		-105/40		-53.33
    QTMI2		0/40		-22.15
    QTMR1		5/35		-2.40
    QTMR2		5/35		-3.58
    
    
    		SUMER
    
    QTSI1A		15/27		-21.40*
    QTSI1B		15/27		-21.40*
    QTSI2A		5/25		-21.40*
    QTSI2B		5/25		-21.40*
    QTSR1		5/35		-0.96
    QTSR2		5/34		-16.27
    QTSR3		2/27		-13.98
    
    
    		SWAN
    
    QTNI1A		5/30		44.45
    QTNI1B		5/30		45.71
    QTNI2A		5/30		-21.40*
    QTNI2B		5/30		-21.40*
    QTNR1		5/35		29.34
    QTNR2		5/35		-21.40*
    QTNR3		6/31		-13.66
    
    
    		UVCS
    
    QTUI1A		0/40		-5.65
    QTUI1B		0/40		-5.36
    QTUR1		5/35		-5.06
    QTUR2		5/30		37.13
    
    
    		VIRGO
    
    QTVR1		3/30		-9.50
    QTVR2		5/33		-18.83		
    
    
    -----------
    Note: * means: end of sensor measurement range
    
    


    9 August 1998

    SOHO telemetry has been restored on Saturday, 8 August 1998 at 23:15 UT. After recharging battery #2 for 10 hours, telemetry was successfully switched on and seven frames of VC0 have been received at GSFC from Goldstone (D24). Telemetry has been switched off after 1 minute to preserve resources. The temperature of the service module is as expected very low. No P/L temperatures are available yet. We are discussing the possibility to try and acquire telemetry today with PRTU ON to get a snapshot of the P/L temperatures. The parts of the power, data handling and telecommunication subsystems used so far behaved nominally. Battery #2 is partially charged (42 V; nominal 46.8 V). Experts in Europe have been contacted for further advice on the management of the batteries.


    7 August 1998

    The Goldstone station has been reconfigured so that partial frames could be recorded and sent out to Goddard. During a 1 hour test late this afternoon we got carrier lock, subcarrier lock and symbol lock for 5 sec. The validity of the data has to be confirmed after processing. The test was limited in order to limit the on/off stress of the units involved.

    A new procedure to charge the batteries will be run over night.

    We were able to get time at Arecibo and DSS14 next Tuesday, August 11. Arecibo will support SOHO radar observations from 1300 to 1600 UT. DSS14 is scheduled for SOHO from 1145 to 2115 UT. The plan is to do S-band bistatic measurements with Arecibo in the slot 1145-1600, and X-band radar ranging from 1600 to 2115 UT. Arecibo will let us know Monday whether the S-band transmitter will be operational. If Arecibo is not operational, the time will be used for SOHO TLM downlink acquisition efforts.


    6 August 1998

    With D24 send/receive and D27 receiving we got many more signal spikes, some of which lasted up to 60 sec. Data modulation on the telemetry subcarrier was confirmed. However, we still have not been able to lock on the subcarrier and demodulate the signal. Efforts are being made to validate the ground system.

    A test was performed using Transmitter 1 (which is connected to the +z low gain antenna). No signal was received. (Commanding through Receiver 2)

    A test with carrier ON only produced spikes of the expected signal strength (-135 dbm).

    A test with the previously unsuccessful switch-on procedure now was successful.

    Tom van Overbeek and colleagues from the simulation section of ESA/ESTEC (TOS-EMM) have produced an MPEG animation of the time period 100-260 sec of the MMS-UK simulation of ESR7 which matches the available telemetry the best way. You can find the MPEG and some other information about the last minutes before the loss of telemetry on June 25 at: http://sohowww.nascom.nasa.gov/operations/ESR7/ or, for our European colleagues, at our mirror site at the Solar Sytem Divsion at ESTEC (SCI-SO): http://sohowww.estec.esa.nl/operations/ESR7/


    5 August 1998

    Today we succeeded to switch on telemetry modulation for periods lasting 2 to 14 sec. Occasionally, the ground station receiver achieved lock, but the duration was too short to decode the telemetry data. Discussions are ongoing with JPL to find ways to decode shorter bursts of telemetry.

    Unfortunately, the radar measurements planned for today could no be performed because a high voltage cable to the Arecibo transmitter in the carriage house has broken. DSS14, which was scheduled to receive Arecibo's signals in bistatic mode, could not be used for monostatic radar measurements because they had no clearance for radar uplink.


    4 August 1998

    The search finally was successful!

    Last evening, August 3, 22:51 UT, after yet another modification of the uplink command sequence, carrier spikes lasting between 2 and 10 sec were received both by DSS42 in Canberra and the ESA station in Perth. >From the repetition rate of the spikes one can deduce a rotation period of about 52 sec. This is in excellent agreement with results reported today by Gregory Black from Cornell, who has done more analysis of the bistatic radar measurements from 23 July. From a Fourier analysis of these data he has extracted the rotation frequency (53sec) and associated harmonics. Two new plots including descriptions are available on his web page at: http://astrosun.tn.cornell.edu/radargroup/SOHO/

    The next steps are to recharge the batteries and try to switch on telemetry modulation.

    DSN coverage:

    Date	DOY	Time		Station
    4/8	216	0835 - 1245	DSS61 Madrid
    4/8	216	1225 - 0030	DSS24 Goldstone
    


    3 August 1998

    The search continues.

    DSN coverage:

    Date	DOY	Time		Station
    1/8	213	0420 - 0920	DSS61 Madrid
    1/8	213	1215 - 2300	DSS13 Goldstone (WBSA)
    1/8	213	1215 - 0015	DSS24 Golstone
    2/8	214	0030 - 0430	DSS42 Canberra
    2/8	214	0425 - 0715	DSS61 Madrid
    2/8	214	1220 - 2045	DSS24 Goldstone
    2/8	214	2115 - 0430/215 DSS34 Canberra
    3/8	215	0430 - 1020	DSS61 Madrid
    3/8 	215	1225 - 1735	DSS24 Goldstone
    3/8	215	2245 - 0500/216 DSS42 Canberra
    


    31 July 1998

    The search continues.

    The Arecibo group is reworking their configuration to attempt a monostatic CW collection next Wednesday, August 5. We are trying to schedule DSS14 at Goldstone to have a backup in case the Arecibo transmit/receive system has problems. In this context one should note that the use of Arecibo to both transmit and receive the echo is complicated by the very short, 10 sec, round trip light time. The Arecibo radar was designed to look at objects at much larger distances so it uses a CW transmitter which takes several seconds to change from transmitting to receiving or vise versa and which involves rotation of a device weighing several tousand pounds. However, if the attempt is successful, it will provide the best data to extract information on the attitude state of SOHO.

    DSN coverage:

    Date	DOY	Time		Station
    31/7	212	0120 - 0430	DSS42 Canberra
    31/7	212	0420 - 0545	DSS61 Madrid
    31/7	212	1215 - 2125	DSS24 Goldstone
    31/7	212	2115 - 0425/213 DSS34 Canberra
    


    30 July 1998

    The search continues.

    DSN coverage:

    Date	DOY	Time		Station
    30/7	211	0415 - 0710	DSS61 Madrid
    30/7	211	1210 - 0030/212	DSS24 Goldstone
    


    29 July 1998

    The search continues.

    The 70 m dish of DSS14 at Goldstone was used for monostatic radar measurements in X-band (8.8 GHz) with an uplink power of 150 kW. Again, a good signal was received at the predicted location. Unfortunately, no ranging measurements could be performed because the ephemeris product needed for the pulse mode operation contained an unexpected character, causing the software to stall. As I understood the colleagues from JPL, this format has been used now for 20 years, and yet they discovered another failure mode! We hope to get 70 m time next week to repeat the ranging measurements. Because of this software problem, only CW (continuous wave) measurements could be performed. Preliminary analysis of these data again are consistent with a spin rate of 1 RPM.

    The analysis of last week's bistatic radar measurements Arecibo-Goldstone is still ongoing. There are several questions which have not yet been conclusively answered. Among them is that of the significance of the spurious slow drift which I've mentioned in my status report of 23 July. This drift seems symmetric with respect to transit at Arecibo. Some people therefore are suspicious whether this is a real effect or related to an instrumental effect. Further, re-calibration of the data by Greg Black from the NAIC group indicates rather large radar cross sections on the order of 15 to 20 m^2, as compared to previous estimates which were on the order of 4 m^2. These somewhat conflicting results may give you a good indication where we stand with the analysis of last weeks measurements.

    Greg Black from NAIC was kind enough to put some of his spectra on the web: http://astrosun.tn.cornell.edu/radargroup/SOHO/soho.html

    Please keep in mind that these are still PRELIMINARY RESULTS!

    DSN coverage:

    Date	DOY	Time		Station
    29/7	210	0415 - 0730	DSS61 Madrid
    29/7	210	1210 - 1540	DSS24 Goldstone
    29/7	210	1410 - 1800	DSS14 Goldstone
    29/7 	210	2100 - 0410	DSS42 Canberra
    


    28 July 1998

    The search continues.

    Nothing definitive yet from the analysis of the radar data. We hope to hear more tomorrow evening in a telecon with JPL after the monostatic run with DSS14 in X-band.

    DSN coverage:

    Date	DOY	Time		Station
    28/7    209	0030 - 0345	DSS42 Canberra
    28/7	209	0415 - 0730	DSS61 Madrid
    28/7	209	1205 - 2355	DSS24 Goldstone
    28/7	209	2335 - 0320/210 DSS42 Canberra
    


    27 July 1998

    The search continues.

    The radar measurements from last week are still being analyzed. Monostatic radar observations in X-band (8.8 GHz) using DSS14 (70 mantenna at Goldstone) are scheduled for Wednesday, July 29, 1240 - 1830 UT.

    DSN coverage:

    Date	DOY	Time		Station
    25/7	206	0405 - 0655	DSS61 Madrid
    25/7	206	1200 - 0030/207 DSS24 Goldstone
    26/7	207	0010 - 0240	DSS42 Canberra
    26/7	207	0405 - 0830	DSS61 Madrid
    26/7	207	1200 - 0015/208 DSS24 Goldstone
    27/7	208	0410 - 0845	DSS61 Madrid
    27/7	208	1205 - 0040/209	DSS24 Goldstone
    


    24 July 1998

    The search continues.

    Radar experts at NAIC (National Astronomy and Ionosphere Center, Cornell University), JPL and the Lincoln Laboratories are working on the data obtained yesterday. Some sample spectra made at the Goldstone antenna site just after the data were taken are available on the web at: http://astrosun.tn.cornell.edu/radargroup/SOHO/ (They are gif screen captures; one is an animation).

    DSN coverage:

    Date	DOY	Time		Station
    24/7	205	0120 - 0430	DSS42 Canberra
    24/7	205	0315 - 0800	DSS61 Madrid
    24/7	205	1200 - 2115	DSS24 Goldstone
    24/7	205	2100 - 0430	DSS42 Canberra
    


    23 July 1998

    The bistatic radar operation Arecibo-Goldstone, which was performed today from 1300 to 1545 UT, seems to have been successful. DSS14 at Goldstone was able to receive strong echos from SOHO at its predicted location. The signal width was 1-2 Hz, which is compatible with a spin rate of about 1 RPM (certainly not much faster). The center frequency drifted slowly by a few Hz. The period of this slow movement must be longer than 2 hours. It may be indicative of a non-principal axis rotation.

    All this results from a very preliminary analysis of data gathered just 6 hours ago. Two teams at JPL and Arecibo are working in parallel on a detailed analysis of the data, hopefully leading to a better understanding of SOHO's attitude. We hope to have more to report by Monday.

    In the meantime, we are trying to schedule a monostatic DSN run in X-band. With half an hour integration time it should be possible to determine the position to +- 20 m. Periodic measurements of this kind should help keep SOHO's ephemeris up-to-date.

    DSN coverage:

    Date	DOY	Time		Station
    23/7	204	0415 - 0730	DSS61 Madrid
    23/7	204	1155 - 2340	DSS24 Goldstone (34 m)
    23/7	204	1300 - 1545	DSS14 Goldstone (70 m; bistatic radar 
    						 with Arecibo)
    


    22 July 1998

    The search continues.

    Tomorrow, 22 July, 1300-1600 UT, there will be a bistatic radar operation Arecibo - Goldstone. The aims of this operation are - to confirm the location of SOHO - provide updates to orbital vectors - possibly provide information on the spin rate and orientation of the spin axis

    DSN coverage:

    Date	DOY	Time		Station
    22/7	203	0415 - 0750	DSS66 Madrid
    22/7	203	1155 - 1445	DSS24 Goldstone
    22/7	203	2040 - 0430/204 DSS42 Canberra
    


    21 July 1998

    The search continues.

    Studies indicate that it may not be unfeasible to locate SOHO using Arecibo radar. On Thursday we will give it a first try using bistatic radar Arecibo - Goldstone. Arecibo has a 1 MW transmitter operating at 2.380 GHz. Goldstone will try to receive the reflected signal with a 70 m dish (DSS14). The team at Arecibo is led by Donald Campbell from Cornell. For more information on Arecibo, see http://www.naic.edu/open.htm

    DSN coverage:

    Date	DOY	Time		Station
    21/7    202     0355 - 0545     DSS61 Madrid
    21/7    202     1155 - 2325     DSS24 Goldstone (+DSS13)
    21/7    202     2305 - 0405/203 DSS34 Canberra
    


    20 July 1998

    The search continues.

    A digital Wide Band Spectrum Analyser (WBSA) which was previously used for the SETI project has been installed at Goldstone. In order to be able to eliminate instrumental effects, it has been set up with two simultaneous feeds from DSS24 and DSS13.

    DSN coverage:

    Date	DOY	Time		Station
    18/7	199	1155 - 2345	DSS24 Goldstone
    19/7	200	0140 - 0425	DSS34 Canberra
    19/7	200	1155 - 2145	DSS24 Goldstone
    19/7	200	2130 - 0345/201	DSS34 Canberra
    20/7	201	0355 - 0800	DSS61 Madrid
    20/7	201	1155 - 0020	DSS24 Goldstone (+ DSS13)
    


    17 July 1998

    The search continues.

    Colleagues operating the Stanford/SRI 150-feet dish joined in the search for a signal from SOHO. Feasibility studies of locating SOHO using Arecibo and DSN radar are ongoing.

    DSN coverage:

    Date	DOY	Time		Station
    17/7	198	0445 - 0810	DSS61 Madrid
    17/7	198	1245 - 2220	DSS24 Goldstone
    17/7	198	2210 - 0245/199 DSS42 Canberra
    


    16 July 1998

    The search continues.

    ESA and NASA have issued a press release "Efforts to recover SOHO spacecraft continue as investigation board focuses on most likely causes". The ESA-NASA Mission Interruption Review Board has issued a preliminary status and background report. Both the press release and the preliminary report are available on the web at http://sohowww.nascom.nasa.gov/whatsnew/

    DSN coverage:

    Date	DOY	Time		Station
    16/7    197   	0540 - 0830	DSS61 Madrid
    16/7	197	1155 - 2345	DSS24 Goldstone
    16/7	197	2320 - 0245/198 DSS42 Canberra
    


    15 July 1998

    The search continues.

    A system is being installed which allows to view the spectrum of the downlink in real time at the EOF.

    DSN coverage:

    Date	DOY	Time		Station
    15/7	196	0010 - 0420	DSS42 Canberra
    15/7	196	0755 - 1135	DSS61 Madrid
    15/7 	196	1155 - 1445	DSS24 Goldstone
    15/7	196	2100 - 0245/197 DSS42 Canberra
    


    14 July 1998

    The search continues.

    This morning RF experts from ESA/ESOC and JPL have arrived to help optimize the search strategy and the set-up of special equipment at the ground stations.

    DSN coverage:

    Date	DOY	Time		Station
    14/7    195     0015 - 0245     DSS42 Canberra
    14/7    195     0830 - 1215     DSS61 Madrid
    14/7    195     1155 - 2250     DSS24 Goldstone
    


    13 July 1998

    DSN stations are continuing to transmit telecommands to RCVR2 at 2067.221 MHz -> 2067.271 MHz in 1.0 kHz steps. Search for downlink signal in frequency interval 2244.945 +- 0.065 MHz.

    DSN coverage:

    Date	DOY	Time		Station
    11/7	192	0710 - 0945	DSS61 Madrid
    11/7	192	1150 - 0000	DSS24 Goldstone
    11/7	192	2340 - 0210/193 DSS42 Canberra
    12/7	193	0715 - 1000	DSS61 Madrid
    12/7   	193	1255 - 0000	DSS24 Goldstone
    13/7   	194	0500 - 0805     DSS61 Madrid
    13/7    194     1155 - 0000     DSS24 Goldstone
    
    The search for a downlink signal at two ESA stations in Perth, Australia and Villafranca, Spain is also continuing, so far without success.


    Bernhard Fleck
    SOHO Project Scientist
    European Space Agency
    bfleck@esa.nascom.nasa.gov



    Last modification: May 29, 2002
    Feedback or questions about this site, please direct to the SOHO Webmaster.