V.Domingo and J.Parkinson gave a report of SIM1 and presented plans for SIM2 which will take place on May 1-5 at the EOF (see annex 11). Aims of SIM2 are:
- Develop realistic operational EOF scenario
- Test entire planning process
- Demonstrate compatibility of fully functional EOF and NASA ground system
- Train instrument teams
Objectives:
- Use realistic S/C and DSN schedule (no accelerated time)
- Use real sun
- Simulate weekly meetings and daily meetings
- Generate daily plans
- Generate command files
- Execute agreed plans
- Receive R/T telemetry + playback
- Respond to (limited) problems
- Create/use Summary Data files
- Display/use other instruments data/observations
- Intensive NRT sessions
Bernhard Fleck