File lasco_sheet4.txt -- Last modified Mon Oct 16 10:57:55 1995 COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: LASCO, Block 4 2. BLOCK IDENTIFICATION: LASCO/EIT HALO ORBIT OPERATIONS 3. PURPOSE: Halo Orbit Operations 4. SUB-BLOCKS: NR. IDENTIFICATION 4.1 Close Doors for Halo Orbit Insertion Maneuver 4.2 Open Doors after Halo Orbit Insertion Maneuver 4.3 Normal Operations 5. SUB-BLOCKS TABLE: NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 4.1 0:20 Block 1 NRT-d H or M Nom. 4.2 0:20 Nom. NRT-d H or M Nom. 4.3 8:00 Nom. NRT-d and s H or M Nom. 6. SCHEDULING REQUIREMENTS: 4.1 must be performed 1 day prior to HOI Maneuver 4.2 must be performed at least 24 hours after HOI Maneuver 4.3 must be performed after 4.2 7. SPECIAL REQUIREMENTS: 4.3 will continue during non-contact periods. 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: Normal operations 9. RELEVANT PROCEDURES None 10. CROSS-REFERENCE TO TEST SHEETS: (list identifiers for test sheets) None 11. RELEVANT SECTION OF TIMELINE: BLOCK4 -- NORMAL OPERATIONS BLOCK4.1 -- CLOSE DOORS FOR HOI MANEUVER 119 & 00:00 # Close C1, C2, C3, EIT Doors BLOCK4.2 -- OPEN DOORS AFTER HOI MANEUVER 121 & 00:00 # Open C1, C2, C3, EIT Doors BLOCK4.3 -- BEGIN LASCO AND EIT HALO ORBIT OPERATIONS 121 & 04:00 # Begin LASCO and EIT Halo Orbit operations ; Synoptic observations ; Susceptibility checks ; Coronal Hole program ; Streamer program ; CME watch program ; Calibrations ; Inter-instrument communication