COMMISSIONING PHASE BLOCK SHEET 1. INSTRUMENT AND BLOCK NUMBER: EIT, Block 2 2. BLOCK IDENTIFICATION: EIT Functional Tests and Calibration 3. PURPOSE: Verify functionality and calibrate EIT 4. SUB-BLOCKS: NR. IDENTIFICATION 2.1 EIT CCD Bakeout Completion 2.2 EIT Internal Calibrations 2.3 Open EIT Door, Calibrations, Close Door 2.4 Open EIT Door, Calibrations, Close Door 2.5 Open EIT Door, EIT Compression Algorithm Calibration 2.6 Begin EIT Nominal Operations (do not schedule for commissioning) 5. SUB-BLOCKS TABLE: NR. - DURATION - PREVIOUS - COMMANDING - TELEMETRY - POINTING 2.1 0:10 Block 1 NRT-d H or M Nom. 2.2 2:00 Nom. NRT-s H or M Nom. 2.3 8:00 Nom. NRT-d and s H or M Nom. 2.4 8:00 Nom. NRT-d and s H or M Nom. 2.5 8:00 Nom. NRT-s H or M Nom. 6. SCHEDULING REQUIREMENTS: Subblocks on subsequent days 7. SPECIAL REQUIREMENTS: (see Note 4) 2.2, 2.3, 2.4 and 2.5 will continue during non-contact periods. 8. SUCCESS CRITERIA AND/OR EXPECTED OUTPUT: EIT functionally verified and calibrated 9. RELEVANT PROCEDURES None